Our expertise and approach
We develop residential, commercial and industrial projects to the highest quality and sustainability standards. At the same time, we place great emphasis on innovation, combining aesthetics and function to create modern, long-term solutions. We also use advanced digital tools and modern techniques to ensure precision and efficiency in every project phase.
Customer focus and way of working
At Arkigroup we always put the customer's needs first, which is why we work closely with our clients throughout the process, from idea and planning to completion. This ensures high quality, clear communication and high customer satisfaction.
How a building permit assignment works
When the assignment covers building permit drawings, we follow six steps, from the first meeting to finished documents.
Initial meeting
By video call, phone or on site, we go through your idea and the material you have, whether it is a sketch, photos or existing drawings.
Analysis and price proposal
We review the conditions and the detailed development plan and prepare a price proposal based on the scope of the project.
Source material
Once you have approved the price proposal, we obtain the material needed, such as a new-build site map and existing drawings from the municipality.
First proposal
We prepare a first proposal in 2D and 3D for you to review at your own pace, and we adjust it together until the drawings match what you want.
Finished building permit drawings
You receive complete drawings, and we help you submit the application to the municipality.
Additional information
If the municipality requests additional information, we help you respond so that the case can move forward.
Technical consultation
When the project requires a certified quality controller, the municipality holds a technical consultation where you go through the technical solutions for the building and the inspection plan.
Start notice
The municipality issues a start notice once it has the documents it needs. You may not start building until you have a start notice, even if the building permit has been granted. For new houses, the municipality normally requires an energy calculation before issuing the start notice.
Start of construction and inspections
Construction follows the approved drawings and the inspection plan. The independent certified quality controller, whom you appoint as the client, checks that the inspections are carried out.
Final consultation
When construction is complete, the municipality may call a final consultation where you go through whether everything has been carried out in line with the building permit and the inspection plan.
Final clearance
Only once the municipality has issued final clearance may you start using the building.
Values
- Right from the start
- We would rather spend an extra hour on the drawing than an extra week on additional information for the municipality.
- Straight answers
- If something cannot be built, or will cost more than you think, we tell you in the very first conversation.
- All the way
- We do not hand over your project halfway. The same firm follows it from sketch to finished building.